Banner OpenAccess

Il sottoattraversamento stradale del Bosforo – Eurasia Tunnel

Rinaldi Giancarlo Cuppone Pierluigi
Articolo Immagine
ISSN:
0393-1641
Rivista:
Gallerie e grandi opere sotterranee
Anno:
2017
Numero:
123
Fascicolo:
Gallerie e grandi opere sotterranee N.123/2017

Acquisto digitale

Acquista:

€ 20.00

Con l’intento di incrementare i collegamenti viari tra la parte asiatica e la parte europea di Istanbul e di alleviare i problemi di traffico, è nato l’Istanbul Strait Road Tube Crossing Project ovvero il progetto dell’attraversamento del Bosforo mediante una galleria sottomarina nota anche come Eurasia Tunnel. L’opera è stata inaugurata nel dicembre del 2016, con 8 mesi di anticipo rispetto al tempo previsto contrattualmente. L’importo complessivo dell’investimento è stato pari a circa 1,25 miliardi di dollari. Il tratto in sotterraneo è lungo circa 5,4 km di cui 3,3 km scavati con TBM di grande diametro (13,71 m). Per le elevate pressioni da contrastare al fronte (11 bar), l’eterogeneità dei terreni (formazione rocciosa denominata Trakia, sedimenti marini, massi erratici) e le condizioni, a tratti, di elevata permeabilità, l’intervento è da considerarsi senza precedenti e decisamente complesso. È stata utilizzata una TBM Mixshield Slurry che ha iniziato lo scavo ad aprile 2014 per concluderlo dopo 16 mesi il 22 agosto del 2015. La velocità di avanzamento è stata mediamente (inclusi i fermi) pari a circa 7 m/giorno con un massimo di 18 m/giorno. Le difficili condizioni in situ e le sollecitazioni a cui sono stati sottoposti i componenti della macchina, hanno comportato attività di manutenzione anche in condizioni iperbariche con pressioni tra gli 8 e i 10 bar. Per tali operazioni si è fatto ricorso a sommozzatori specializzati che per eliminare i tempi necessari alla decompressione, sono stati tenuti costantemente in ambiente iperbarico mediante navetta di trasporto ed apposita camera iperbarica posta all’esterno della galleria. La galleria è dotata di due giunti sismici in corrispondenza delle due aree di contatto tra sedimenti a diversa rigidezza. L’intervento è stato oggetto di diversi riconoscimenti per la sua unicità e difficoltà ed ha attratto l’interesse internazionale degli addetti del settore.

The roadway under Bosphorus – Eurasia Tunnel. 

Following ideas to link Asian and European part of Istanbul by undersea tunnel and to reduce traffic problems, it has been developed of the Istanbul Strait Road Tube Crossing Project that allowed passage of the Bosphorus through a submarine tunnel, now known as Eurasia Tunnel (Avrasya Tunneli in Turkish). After the international tender, the Ministry of Transport, Maritime Affairs and Communications and AYGM entrusted ATAŞ design, construction, financing, management and finally transfer of the construction to the State, using B.O.T. (Build Operate and Transfer) model. The construction works are executed by YMSK Joint Venture, formed by the Turkish Yapı Merkezi and South Korean SK E&C (Companies that are also part of ATAŞ). In January 2013 works on site started (after a preparatory phase begun in 2011). The Eurasia Tunnel was inaugurated on December 20th, 2016, with 8 months in advance of scheduled time. The total investment amounted is approximately $ 1.25 billion. Several international construction and engineering company were involved, participating in different stages of works. Italferr together with Turkish Altnınok, in May 2014, was awarded to supervise the works as the Employer’s Representative (wich is AYGM). The project route (14.6 km) is an interintercontinental road link under Bosphorus, between the Kazliçeşme district in the European side and Göztepe districts located in the Asian area, . The underground section is about 5.4 km long, of which 3.34 km are excavated by TBM. Considering the large excavation diameter (13.71 m), the high pressures (11 bar), the heterogeneity of the soil (Trakya formation, marine sediments and erratic geology) and condition of high permeability, intervention is to be considered unprecedented and definitely problematic. Herrenknecht designed and built the TBM Mixshield Slurry used for excavation, a very versatile machine among the largest and with performance capabilities among highest in the world. Slurry technology has proven to be particularly suitable for the task. During the excavation it was possible to replace hundreds of cutterhead elements, mostly under atmospheric pressure. The machine bored section is about 3.340 m in length. Excavation started in April 2014 and ended 16 months later, on August 22nd, 2015. The average advancement was ca 7 m/day with a maximum peak of 18 m/day. The difficult excavation conditions and the stresses to which the machine components were exposed, including the presence of erratic geology, required maintenance even under hyperbaric conditions. This occurred for 4 times (total time about 6 weeks) under pressures between 8 and 10 bar. For such operations, skilled divers have been recruited. To eliminate time needed for decompression, the divers were constantly in the hyperbaric environment, working within the machine and then, during the rest period, transported by a pressurized shuttle into a special hyperbaric chamber placed outside the tunnel. The tunnel lining has an outside diameter of 13.2 m, an inside diameter of 12.0 m and the rings are consisted of 9 segments (8 + 1 key). Istanbul is located in seismic zone of high risk, near the tunnel track, about 17 km, there is the North Anatolian Fault Zone. In order to allow the tunnel to face seismic events safely, it is equipped with two seismic joints in two contact areas between Trakya and marine sediments (due to different behavior of those geological formations under earthquake conditions). Seismic joints are made by special designed rings which, in the central part allowing structural deformation under the action caused by an earthquake. The seismic joints displacement capacities are ± 75 mm for extension/contraction and ± 51 mm shear offset. The project, being particularly complex and unique, attracted international interest and recognition winning several awards.